Home: Ranchos Las Lomas Community News

November 2006

November 30th, 2006

Pool and deck completed. 2 bedroom 1-1/2 bath villa completed.

October 2006

October 31st, 2006

Interior road system 100% cut and gravel in place. Stump removal continued.

September 2006

September 30th, 2006

Water lines installed in all roads. Prime ocean view lots road cut and gravel installed. Road cut through lot 61.

August 2006

August 31st, 2006

Rancho building of 2,000 square feet completed with metal roof and stone floor. Clean-out of woods near stream.

July 2006

July 31st, 2006

Catastro plans filed for 30 Lots. First sale settles with transfer of clear title Lot #2. Dug well and installed pump. Guard house and entry gate completed. Lot marker for lots 25 thru 45 in place.

June 2006

June 30th, 2006

Road cut for pool, rancho (recreational building) and 20 villas. Gravel road in place for 25 lots. First sale settles with transfer of clear title Lot #2. On going site clean-up.

May 2006

May 31st, 2006

Surveyor lays out 25 lots. Road cut for 25 lots. Razed farm house. Removed scrub growth. Lot markers in place.

Project Progress Log: April 2006

April 30th, 2006

Settled on property. Purchased backhoe and dump truck. Commenced site work. Electric and water connection already in place for existing farmhouse. Site clean-up started.

 

 

Ranchos Las Lomas Blog is proudly powered by WordPress
Entries (RSS) and Comments (RSS).